{"MatterTextId":32945,"MatterTextGuid":"F65AE1C1-AEE3-41AD-8385-D92599522308","MatterTextLastModifiedUtc":"2026-10-30T15:22:06.913","MatterTextRowVersion":"AAAAAAFhEnY=","MatterTextMatterId":31062,"MatterTextVersion":"1","MatterTextPlain":"..Title\nConsider/Discuss/Act on a Resolution Authorizing the City Manager to Execute an Amendment to the Construction Manager at Risk (CMAR) Contract with Crossland Construction Company, Inc. for Additional Construction Services Related to the Police Department Gun Range Improvements and Support Building Project (FC1820/FP1820)\n..Summary\nCOUNCIL GOAL:\tSafe and Secure Community\n\t(6.3: Continually Increase Operational Efficiency in Public Safety\n\tDepartments)\nMEETING DATE:\tNovember 17, 2026\nDEPARTMENT: \tPublic Works Department / Facilities Construction Division\n\tPolice Department\nCONTACT:\tRyan Gillingham, PE, Director of Public Works\n\tPatricia L. Jackson, PE, RAS, Facilities Construction Manager \n\tJoe Ellenburg, Chief of Police\nRECOMMENDED CITY COUNCIL ACTION:\t\nApproval of the Resolution.\nITEM SUMMARY:  \nThis Resolution authorizes the City Manager to execute an amendment to the Construction Manager at Risk (CMAR) contract with Crossland Construction Company, Inc. for additional construction services related to the Police Department Gun Range Improvements and Support Building Project (FP1820/FC1820).\nThe project includes construction of approximately 2,400-square-foot storage and workshop building with restrooms, together with pavement replacement at the Police Department Gun Range. \nAdditional construction work is necessary to address unforeseen field conditions encountered during the project, including adjustments associated with the civil plans, structural piers, and water and irrigation systems. \nTo maintain the project within its original approved budget, an Owner’s contingency was not included in the initial contract with Crossland. Additional work performed to date has been funded through the Contractor’s contingency. The proposed contract amendment will replenish those funds and establish an Owner’s contingency, with a requested authorization not to exceed $75,000, to address additional project needs as they arise.\nBACKGROUND INFORMATION:  \nThe Police Department Gun Range Improvements and Support Building Project includes an approximately 2,400-square-foot storage and workshop building with restrooms and replacement of existing pavement. During construction, unforeseen field conditions required adjustments to the civil plans, structural piers, and water and irrigation systems. The proposed amendment will address additional construction work associated with these field conditions.\nCrossland Construction Company, Inc. serves as the Construction Manager at Risk (CMAR) for the project. Under the CMAR delivery method, the contractor coordinated bidding and subcontractor scope reviews and developed a Guaranteed Maximum Price (GMP) for City Council consideration.\nOn May 19, 2026, City Council approved Resolution agenda item 26-0459 authorizing a GMP contract with Crossland for the Police Department Gun Range Improvements and Support Building Project (FGP1820/FC1820), in an amount not to exceed $1,119,956.\nThe Original GMP approval anticipated construction completion in May 2027. The proposed amendment addresses additional work related to unforeseen site conditions encountered after the GMP was established.\nFINANCIAL SUMMARY:  \nOn May 19, 2026, City Council authorized a Construction Manager at Risk (CMAR) Guaranteed Maximum Price (GMP) contract with Crossland in an amount not to exceed $1,119,956. To remain within the approved project budget, an Owner’s contingency was not included in the original contract, and additional construction work has been funded through the Contractor’s contingency. The proposed contract amendment includes funding to establish an Owner’s contingency for remaining project needs, for a total additional authorization not to exceed $75,000. \nThere is a companion agenda item for Conduit Architecture + Design, LLC for additional design services related to this project. Following approval of this agenda item and the companion agenda item for design, $5,184 will remain in FP1820/FC1820.\nSource of Funds\n\tAmount\n\t\n\tOverall Project Budget (FP1820/FC1820)\n\t$1,378,712\n\t\n\tAnticipated Project Expenses\n\tAmount\n\t\n\tDesign Services — Conduit Architecture\n\t$98,250\n\t\n\tAdditional Design Services – Conduit (Proposed)\n\t$15,000\n\t\n\tConstruction Services / Crossland GMP\n\t$1,119,956\n\t\n\tOwner’s Contingency – Crossland Amendment (Proposed)\n\t$75,000\n\t\n\tOwner’s Rep Services \n\t$15,300\n\t\n\tConstruction Materials Testing Services - Terracon\n\t$34,842\n\t\n\tBuilding Systems Commissioning \n\t$8,580\n\t\n\tGeotechnical Engineering – PSI\n\t$6,600\n\t\n\tProject Contingency / Other Project Costs\n\tTBD\n\t\n\tTOTAL\n\t$1,373,528\n\t\n\tBalance\n\tAmount   \n\t\n\tAvailable Project Funding After Approvals\n\t$5,184\n\t\n\t\nBOARD OR COMMISSION RECOMMENDATION:\nN/A\n\n","MatterTextRtf":"{\\rtf1\\fbidis\\ansi\\ansicpg1252\\deff0\\deflang1033\\deflangfe1033{\\fonttbl{\\f0\\fswiss\\fprq2\\fcharset0 Arial;}{\\f1\\froman\\fprq2\\fcharset0 Times New Roman;}{\\f2\\froman\\fprq2\\fcharset2 Symbol;}}\n\\viewkind4\\uc1\\pard\\ltrpar\\qj\\b\\f0\\fs24 ..Title\\par\n\\pard\\ltrpar\\sa120\\qj\\b0 Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute an Amendment to the Construction Manager at Risk (CMAR) Contract with Crossland Construction Company, Inc. for Additional Construction Services Related to the Police Department Gun Range Improvements and Support Building Project (FC1820/FP1820)\\par\n\\pard\\ltrpar\\sa120\\qj\\tx720\\tqc\\tx4320\\tqr\\tx8640\\b ..Summary\\par\n\\pard\\ltrpar\\tx2160\\tqc\\tx4320\\tqr\\tx8640 COUNCIL GOAL:\\tab\\b0 Safe and Secure Community\\par\n\\tab (6.3: Continually Increase Operational Efficiency in Public Safety\\par\n\\pard\\ltrpar\\sa120\\tx2160\\tqc\\tx4320\\tqr\\tx8640\\f1\\tab\\f0 Departments)\\par\n\\pard\\ltrpar\\sa120\\tx720\\tx2160\\tqc\\tx4320\\tqr\\tx8640\\b MEETING DATE:\\tab\\b0 November 17, 2026\\par\n\\pard\\ltrpar\\tx2160\\tqc\\tx4320\\tqr\\tx8640\\b DEPARTMENT:\\b0  \\tab Public Works Department / Facilities Construction Division\\par\n\\pard\\ltrpar\\sa120\\tx2160\\tqc\\tx4320\\tqr\\tx8640\\tab Police Department\\b\\par\n\\pard\\ltrpar\\fi-2160\\li2160\\tx2160\\tqc\\tx4320\\tqr\\tx8640 CONTACT:\\tab\\b0 Ryan Gillingham, PE, Director of Public Works\\par\n\\b\\tab\\b0 Patricia L. Jackson, PE, RAS, Facilities Construction Manager \\par\n\\pard\\ltrpar\\fi-2160\\li2160\\sa120\\tx2160\\tqc\\tx4320\\tqr\\tx8640\\tab Joe Ellenburg, Chief of Police\\f1\\par\n\\pard\\ltrpar\\qj\\tx720\\tqc\\tx4320\\tqr\\tx8640\\b\\f0 RECOMMENDED CITY COUNCIL ACTION:\\tab\\par\n\\pard\\ltrpar\\fi-360\\li720\\sa120\\tx720\\tqc\\tx4320\\tqr\\tx8640\\b0\\f2\\'b7\\tab\\f0 Approval of the Resolution.\\b\\par\n\\pard\\ltrpar\\qj\\tx720\\tqc\\tx4320\\tqr\\tx8640 ITEM SUMMARY:  \\par\n\\pard\\ltrpar\\fi-360\\li720\\sa120\\qj\\tx720\\tqc\\tx4320\\tqr\\tx8640\\b0\\f2\\'b7\\tab\\f0 This Resolution authorizes the City Manager to execute an amendment to the Construction Manager at Risk (CMAR) contract with Crossland Construction Company, Inc. for additional construction services related to the Police Department Gun Range Improvements and Support Building Project (FP1820/FC1820).\\par\n\\pard\\ltrpar\\fi-360\\li720\\sa120\\qj\\f2\\'b7\\tab\\f0 The project includes construction of approximately 2,400-square-foot storage and workshop building with restrooms, together with pavement replacement at the Police Department Gun Range. \\par\n\\f2\\'b7\\tab\\f0 Additional construction work is necessary to address unforeseen field conditions encountered during the project, including adjustments associated with the civil plans, structural piers, and water and irrigation systems. \\par\n\\kerning2\\f2\\'b7\\tab\\f0 To maintain the project within its original approved budget, an Owner\\rquote s contingency was not included in the initial contract with Crossland. Additional work performed to date has been funded through the Contractor\\rquote s contingency. The proposed contract amendment will replenish those funds and establish an Owner\\rquote s contingency, with a requested authorization not to exceed $75,000, to address additional project needs as they arise.\\kerning0\\par\n\\pard\\ltrpar\\tx720\\tqc\\tx4320\\tqr\\tx8640\\b BACKGROUND INFORMATION: \\b0  \\par\n\\pard\\ltrpar\\fi-360\\li720\\sa120\\sl252\\slmult1\\qj\\tx720\\tqc\\tx4320\\tqr\\tx8640\\f2\\'b7\\tab\\f0 The Police Department Gun Range Improvements and Support Building Project includes an approximately 2,400-square-foot storage and workshop building with restrooms and replacement of existing pavement. During construction, unforeseen field conditions required adjustments to the civil plans, structural piers, and water and irrigation systems. The proposed amendment will address additional construction work associated with these field conditions.\\b\\par\n\\pard\\ltrpar\\fi-360\\li720\\sa120\\sl252\\slmult1\\qj\\b0\\f2\\'b7\\tab\\f0 Crossland Construction Company, Inc. serves as the Construction Manager at Risk (CMAR) for the project. Under the CMAR delivery method, the contractor coordinated bidding and subcontractor scope reviews and developed a Guaranteed Maximum Price (GMP) for City Council consideration.\\b\\par\n\\b0\\f2\\'b7\\tab\\f0 On May 19, 2026, City Council approved Resolution agenda item 26-0459 authorizing a GMP contract with Crossland for the Police Department Gun Range Improvements and Support Building Project (FGP1820/FC1820), in an amount not to exceed $1,119,956.\\b\\par\n\\b0\\f2\\'b7\\tab\\f0 The Original GMP approval anticipated construction completion in May 2027. The proposed amendment addresses additional work related to unforeseen site conditions encountered after the GMP was established.\\b\\par\n\\pard\\ltrpar\\qj\\tx720\\tqc\\tx4320\\tqr\\tx8640 FINANCIAL SUMMARY:  \\par\n\\pard\\ltrpar\\fi-360\\li720\\sa120\\sl252\\slmult1\\qj\\tx720\\tqc\\tx4320\\tqr\\tx8640\\b0\\f2\\'b7\\tab\\f0 On May 19, 2026, City Council authorized a Construction Manager at Risk (CMAR) Guaranteed Maximum Price (GMP) contract with Crossland in an amount not to exceed $1,119,956. To remain within the approved project budget, an Owner\\rquote s contingency was not included in the original contract, and additional construction work has been funded through the Contractor\\rquote s contingency. The proposed contract amendment includes funding to establish an Owner\\rquote s contingency for remaining project needs, for a total additional authorization not to exceed $75,000. \\par\n\\pard\\ltrpar\\fi-360\\li720\\sa240\\qj\\tx720\\tqc\\tx4320\\tqr\\tx8640\\f2\\'b7\\tab\\f0 There is a companion agenda item for Conduit Architecture + Design, LLC for additional design services related to this project. Following approval of this agenda item and the companion agenda item for design, $5,184 will remain in FP1820/FC1820.\\par\n\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\pard\\intbl\\ltrpar\\sl276\\slmult1\\b Source of Funds\\b0\\f1\\cell\\b\\f0 Amount\\b0\\f1\\cell\\kerning2\\row\n\\kerning0\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Overall Project Budget (FP1820/FC1820)\\f1\\cell\\f0 $1,378,712\\f1\\cell\\kerning2\\row\n\\kerning0\\b\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Anticipated Project Expenses\\b0\\f1\\cell\\b\\f0 Amount\\b0\\f1\\cell\\kerning2\\row\n\\kerning0\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Design Services - Conduit Architecture\\f1\\cell\\f0 $98,250\\f1\\cell\\kerning2\\row\n\\kerning0\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Additional Design Services - Conduit (Proposed)\\cell $15,000\\cell\\kerning2\\f1\\row\n\\kerning0\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Construction Services / Crossland GMP\\f1\\cell\\f0 $1,119,956\\f1\\cell\\kerning2\\row\n\\kerning0\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Owner\\rquote s Contingency - Crossland Amendment (Proposed)\\cell $75,000\\cell\\kerning2\\f1\\row\n\\kerning0\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Owner\\rquote s Rep Services \\f1\\cell\\f0 $15,300\\f1\\cell\\kerning2\\row\n\\kerning0\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Construction Materials Testing Services - Terracon\\f1\\cell\\f0 $34,842\\f1\\cell\\kerning2\\row\n\\kerning0\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Building Systems Commissioning \\cell $8,580\\cell\\kerning2\\f1\\row\n\\kerning0\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Geotechnical Engineering - PSI\\cell $6,600\\cell\\kerning2\\f1\\row\n\\kerning0\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Project Contingency / Other Project Costs\\f1\\cell\\f0 TBD\\f1\\cell\\kerning2\\row\n\\kerning0\\b\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl TOTAL\\f1\\cell\\b0\\f0 $1,373,528\\cell\\kerning2\\f1\\row\n\\kerning0\\b\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Balance\\cell Amount   \\cell\\kerning2\\b0\\f1\\row\n\\kerning0\\f0\\trowd\\trgaph108\\trleft5\\trqc\\trbrdrt\\brdrs\\brdrw10 \\trbrdrl\\brdrs\\brdrw10 \\trbrdrb\\brdrs\\brdrw10 \\trbrdrr\\brdrs\\brdrw10 \\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx6601\\clbrdrt\\brdrw15\\brdrs\\clbrdrl\\brdrw15\\brdrs\\clbrdrb\\brdrw15\\brdrs\\clbrdrr\\brdrw15\\brdrs \\cellx8831\\intbl Available Project Funding After Approvals\\cell $5,184\\cell\\kerning2\\f1\\row\n\\pard\\ltrpar\\tx720\\tqc\\tx4320\\tqr\\tx8640\\kerning0\\b\\f0\\par\nBOARD OR COMMISSION RECOMMENDATION:\\par\n\\pard\\ltrpar\\fi-360\\li720\\sa120\\sl276\\slmult1\\qj\\tx720\\tqc\\tx4320\\tqr\\tx8640\\b0\\f2\\'b7\\tab\\f0 N/A\\kerning2\\f1\\par\n\\pard\\ltrpar\\sa160\\sl276\\slmult1\\par\n}\n"}